ceiling gib

Started the ceiling in the lounge this week and it was a very good learning experience for our group. When we had to pull a sheet down, we learnt the difference between T/E and T/E S/E.









Monday, March 28, 2011

ccb

Some images of recent activities with insulation. It's important that insulation is fitted snug so the R value is achieve but not too compact otherwise we effect the K value. We are using R3.2 for ceilings and R2.2 for walls.

Tuesday, March 8, 2011

old school



It was one of those days where battery drills where like GOLD, if you put one down without standing on it, then it would surely disappear. So Kim and Setu resorted to desperate measures with great success.

Saturday, February 12, 2011

Building remedial work (entry 2)

Incorrect Footing for Brick Veneer.


What is the required Width for a Brick Veneer footing to rest on?

What is the required step down for the Brick veneer footing from the FFL?

Building remedial work (entry 1)

This first entry is about the deck that was originally built at a height above FFL and laid with a waterproof decking system as opposed to a slated deck that is drawn on the plans. The roof above needed to be supported so that the deck below could be demolished and rebuilt.




Images on Picasa:


These photos show the upper roof being supported by scaffolding while the deck below is being reconstructed.